GIAC GCPM Exam - Topic 7 Question 75 Discussion

Which of the following statements about Work Breakdown Structure (WBS) are true? Each correct answer represents a complete solution. Choose all that apply.
A) It defines a project and groups the project's discrete work elements in a way that helps to organize and define the total work scope of the project. and C) It provides a framework for detailed cost estimating and control along with providing guidance for schedule development and control. and D) It is an important project management tool.
B) It cannot be revised and updated as needed by the project manager.

GIAC GCPM Exam - Topic 7 Question 75 Discussion

Actual exam question for GIAC's GCPM exam
Question #: 75
Topic #: 7
[All GCPM Questions]

Which of the following statements about Work Breakdown Structure (WBS) are true? Each correct answer represents a complete solution. Choose all that apply.

Show Suggested Answer Hide Answer
Suggested Answer: A, C, D

Contribute your Thoughts:

0/2000 characters
Rhea
4 months ago
I think A), C), and D) are the best choices.
upvoted 0 times
...
Ashton
4 months ago
D) is also true. WBS is crucial for project management.
upvoted 0 times
...
Nida
5 months ago
B) is false. WBS can be updated as the project evolves.
upvoted 0 times
...
Clorinda
5 months ago
I agree, A) is essential for defining scope.
upvoted 0 times
...
Chun
5 months ago
A) and C) are definitely true. They help in organizing the project.
upvoted 0 times
...
Glenna
5 months ago
A is correct, it really helps in organizing the work!
upvoted 0 times
...
Theodora
5 months ago
Wait, can WBS really be revised? I thought it was set in stone.
upvoted 0 times
...
Luke
5 months ago
D is spot on, it's super important for projects!
upvoted 0 times
...
Coral
6 months ago
I disagree with B, WBS can be updated.
upvoted 0 times
...
Coral
6 months ago
A, C, and D are the winners here. WBS is the project manager's best friend.
upvoted 0 times
...
Louis
6 months ago
B is just silly. Of course the WBS can be updated! How else would we keep up with all the changes?
upvoted 0 times
...
Dong
7 months ago
A, C, and D are spot on. WBS is like a roadmap for the project - can't live without it!
upvoted 0 times
...
Chi
7 months ago
All of the options except B are correct. WBS can definitely be revised as needed.
upvoted 0 times
...
Glendora
7 months ago
I feel like I’ve seen questions like this before, and I think A, C, and D are the right answers.
upvoted 0 times
...
Wayne
7 months ago
D seems obvious since we always referred to WBS as a key tool in our studies.
upvoted 0 times
...
Lasandra
7 months ago
I’m not sure about B; I thought WBS could be updated as the project evolves.
upvoted 0 times
...
Shannan
7 months ago
I remember that a WBS is crucial for defining the scope, so I think A and C are definitely true.
upvoted 0 times
...
Nohemi
8 months ago
I know a WBS can be revised and updated as needed, so statement B must be false. The other statements sound right, but I'll double-check to be sure.
upvoted 0 times
...
Matthew
8 months ago
Okay, I remember that a WBS is meant to help organize and define the project scope, so statement A seems correct. But I'm not sure about the other statements - I'll have to think through them.
upvoted 0 times
...
Van
8 months ago
A WBS is definitely an important project management tool, so I'm confident that statement D is true. The other ones I'll have to analyze more closely.
upvoted 0 times
...
Kimberely
8 months ago
A and C are definitely true. WBS helps organize the work and provides a framework for cost and schedule control.
upvoted 0 times
...
Nikita
8 months ago
A, C, and D are correct. WBS is a crucial tool for project management.
upvoted 0 times
...
Jani
9 months ago
A) and C) are definitely true!
upvoted 0 times
...
Romana
9 months ago
Yes, WBS is vital for cost and schedule control.
upvoted 0 times
...
Kimbery
9 months ago
Hmm, I'm a little unsure about the specifics of WBS. I'll need to think through each statement carefully to determine which ones are true.
upvoted 0 times
...
Merissa
9 months ago
This looks like a pretty straightforward question on WBS. I'll start by reviewing what I know about the key features and uses of a WBS.
upvoted 0 times
Brett
4 months ago
All the correct options help in project clarity!
upvoted 0 times
...
Carissa
4 months ago
B) is false. It can be updated as the project evolves.
upvoted 0 times
...
Alpha
4 months ago
D) for sure! WBS is crucial for project management.
upvoted 0 times
...
Lorrie
4 months ago
C) is also correct. It aids in cost estimating.
upvoted 0 times
...
Caitlin
8 months ago
A) is definitely true. It helps in organizing the project.
upvoted 0 times
...
...