You work as a project manager for company Inc. Management has selected the team members for your team in advance. Which of the following techniques of the Acquire project team has been used in the above scenario?
Suggested Answer: A
Get Premium GCPM Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
12 comments · newest first
OL
Oliva
2 months ago
I’m not so sure. Could it be B) Acquisition? But I lean towards A too.
LI
Lizette
2 months ago
Agreed! Pre-assignment fits. It shows management's control over the team.
PA
Paul
2 months ago
I think it's A) Pre-assignment. Makes sense since the team was chosen beforehand.
RU
Rusty
2 months ago
Nah, it's A) Pre-assignment for sure. No doubt about it!
HO
Hoa
2 months ago
Wait, are we sure it's not C) Virtual team? Seems odd.
AN
Anika
2 months ago
I agree with A. Makes sense for a project team.
JI
Jill
3 months ago
I think it could be B) Acquisition too.
HU
Huey
3 months ago
Definitely A) Pre-assignment. That's how it works!
RO
Rose
3 months ago
I’m a bit lost here. Could it be negotiation? I remember that term being used in team selection discussions.
MI
Miesha
3 months ago
This sounds familiar; I feel like I've seen a question like this before, and pre-assignment seems to fit best.
KR
Kristofer
3 months ago
I'm not entirely sure, but I remember something about acquisition being about bringing in external resources.
EA
Earleen
4 months ago
I think this might be related to pre-assignment since the team members were chosen before the project started.