GIAC Exam GCPM Topic 8 Question 42 Discussion

Actual exam question for GIAC's GIAC Certified Project Manager exam
Question #: 42
Topic #: 8
[All GIAC Certified Project Manager Questions]

You work as a project manager for company Inc. You are working on a project that has a budget of $805,000 and you have completed 45 percent of the project work. Due to some errors, however, you have actually spent $430,000 of the budget. Management wants to know the project's cost performance index. Which of the following values will you report?

Show Suggested Answer Hide Answer
Suggested Answer: D

Comments

Naomi
1 days ago
Okay, let's think this through step-by-step. We've got the budget, the percentage of work completed, and the actual amount spent. Shouldn't be too hard to figure out the cost performance index.
upvoted 0 times
...
Ilda
3 days ago
Wow, this question seems tricky! I'm not sure I'm fully prepared for this kind of calculation in the exam.
upvoted 0 times
...