GIAC Exam GCPM Topic 1 Question 49 Discussion

Actual exam question for GIAC's GCPM exam
Question #: 49
Topic #: 1
[All GCPM Questions]

You work as a project manager for company Inc. The company has recently opened a new department in its main building. You need information of all the vendors and hardware equipment being used in the different areas of the newly built department. Which of the following charts will you use to get the required information?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Haydee
3 months ago
The PBS (Product Breakdown Structure) might be a good choice too, as it outlines the various components and deliverables of the project. But I'm still leaning towards the WBS as the most comprehensive option.
upvoted 0 times
...
Bettina
3 months ago
Haha, this is a tough one. I bet the project manager is going to need a crystal ball to figure this out! But seriously, I think the WBS is the way to go here.
upvoted 0 times
Carey
2 months ago
I'm not sure, but I think the PBS might be helpful in organizing the different areas of the new department.
upvoted 0 times
...
Mable
2 months ago
I think the RBS might also be useful in this situation to track resources being used in the new department.
upvoted 0 times
...
Svetlana
2 months ago
I agree, the WBS is the best option for getting information on vendors and hardware equipment.
upvoted 0 times
...
...
Belen
3 months ago
I'm going with D) RBS (Risk Breakdown Structure). This will help identify any potential risks associated with the vendors and hardware equipment, right? That's what I would use to get the required information.
upvoted 0 times
Nida
2 months ago
OBS (Organizational Breakdown Structure) could help in understanding the roles and responsibilities of the vendors and staff in the new department.
upvoted 0 times
...
Jamika
2 months ago
I think WBS (Work Breakdown Structure) would also be useful to organize and categorize the different areas and tasks in the new department.
upvoted 0 times
...
Beckie
2 months ago
Yes, RBS is the correct choice for identifying risks associated with vendors and hardware equipment.
upvoted 0 times
...
...
Rhea
4 months ago
Hmm, I'm not sure. Maybe the OBS (Organizational Breakdown Structure) would be more appropriate since it shows the hierarchical structure of the organization, including the new department.
upvoted 0 times
Sheridan
2 months ago
I agree, the WBS breaks down the project into smaller, manageable components which would help in gathering information about vendors and hardware equipment.
upvoted 0 times
...
Kate
2 months ago
I think the WBS (Work Breakdown Structure) would be more suitable for this task.
upvoted 0 times
...
Kandis
3 months ago
D) RBS
upvoted 0 times
...
Arlyne
3 months ago
C) OBS
upvoted 0 times
...
Nobuko
3 months ago
B) WBS
upvoted 0 times
...
Wava
3 months ago
A) PBS
upvoted 0 times
...
...
Alease
4 months ago
I would also consider using the RBS chart, as it can provide detailed information about the resources being used.
upvoted 0 times
...
Raina
4 months ago
I think the correct answer is B) WBS. The Work Breakdown Structure should provide the detailed information on all the vendors and hardware equipment used in the different areas of the newly built department.
upvoted 0 times
Josefa
2 months ago
Let's make sure to update the WBS with all the necessary information for the new department.
upvoted 0 times
...
Emeline
2 months ago
Yes, the WBS is designed to provide a detailed overview of the project scope and resources.
upvoted 0 times
...
Domitila
2 months ago
I think the WBS will give us a clear breakdown of all the vendors and hardware equipment.
upvoted 0 times
...
Rodolfo
3 months ago
I agree, the WBS is the best chart to use for that information.
upvoted 0 times
...
...
Cordelia
4 months ago
I agree with Ryan, WBS would be the best option for this.
upvoted 0 times
...
Ryan
4 months ago
I think I would use the WBS chart to get the information.
upvoted 0 times
...

Save Cancel