GAQM ISO-BCMS-22301 Exam - Topic 5 Question 1 Discussion

Actual exam question for GAQM's ISO-BCMS-22301 exam
Question #: 1
Topic #: 5
[All ISO-BCMS-22301 Questions]

Which phase in PDCA cycle assesses the effectiveness of the BCMS against requirements of the business continuity policy?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

0/2000 characters
Santos
4 months ago
Really? I always thought it was more about the Plan phase.
upvoted 0 times
...
Noel
4 months ago
Nope, definitely Check. That's the assessment stage.
upvoted 0 times
...
Nickole
4 months ago
Wait, I thought it was the Act phase?
upvoted 0 times
...
Virgie
4 months ago
Totally agree, Check is where you measure success!
upvoted 0 times
...
Miesha
5 months ago
It's the Check phase that evaluates effectiveness.
upvoted 0 times
...
Niesha
5 months ago
If I recall correctly, "Check" is where we evaluate how well the BCMS meets the policy requirements.
upvoted 0 times
...
Chandra
5 months ago
I remember practicing a similar question, and I think "Act" is about making improvements after checking, right?
upvoted 0 times
...
Edmond
5 months ago
I think the phase that assesses effectiveness is the "Check" phase, but I'm not entirely sure.
upvoted 0 times
...
Robt
5 months ago
I'm a bit confused between "Check" and "Do." I feel like both involve some level of assessment.
upvoted 0 times
...
Eun
5 months ago
The key detail I'm focusing on is that the question says the "Highlight" button is "present in UiExplorer". That makes me think it's always available, not just when the selector is valid or invalid. So I'm leaning towards option A or C as the correct answer.
upvoted 0 times
...
Veda
5 months ago
I'm a bit confused by the wording of this question. Are the options describing different payment methods or just different ways of handling payments? I'll have to read through it again to make sure I understand.
upvoted 0 times
...
Sabrina
5 months ago
Okay, let me think this through. I need to create a new route for the 10.10.22.0/24 subnet using the 30.30.30.158 gateway. I'll go with option B.
upvoted 0 times
...

Save Cancel