Which of the following are product risks and which are project risks?
a.The navigation through some parts of the website may need to be different from others.
b.Sprint 1 may not be completed on time, leading to a delay to the start of Sprint 2.
c.Text versions of images may not always be possible.
d.There may be a need to buy a capture-replay tool for regression testing.
key member of the team may leave before the Sprints have been completed.
Suggested Answer: B
Get Premium CTIL-001 Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
12 comments · newest first
NI
Nikita
12 months ago
I’m not so sure about d being a product risk.
CE
Cecilia
12 months ago
I agree with B, makes the most sense.
CA
Candra
1 year ago
Surprised that e is considered a risk at all!
NO
Norah
1 year ago
Nah, b is a project risk for sure.
KI
Kimbery
1 year ago
I think a and c are definitely product risks.
CH
Cherry
1 year ago
I thought project risks were about resources and schedules, so b and e seem to fit that, but I’m not confident about the others.
TR
Trevor
1 year ago
I feel like we had a similar question in practice, and I think a and c are definitely product risks, but I'm confused about d.
LA
Lavonne
1 year ago
I remember we discussed how product risks are related to the final outcome, like the navigation issues or text versions of images.
MA
Malinda
1 year ago
I'm not entirely sure, but I think project risks are more about timelines, so maybe b and e are project risks?
MA
Mary
1 year ago
This question seems pretty straightforward. I think I can handle this one.
CA
Cathrine
1 year ago
I've got this! Decreasing the epsilon parameter will add more noise to the data, which reduces the accuracy but increases the privacy. That's exactly what the question is asking for.
IS
Isabella
1 year ago
I'm leaning towards route leaking; I feel like we discussed it in relation to VNs connecting across the fabric border nodes.