A company has two datacenters in different cities. When one of the datacenters loses power, there is near instant failover to the other datacenter. This is an example of which of the following?

Suggested Answer: B

Get Premium CCCP-001 Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
13 comments · newest first
DA
Daniel 12 months ago
I disagree, warm sites can also do failover.
JU
Junita 12 months ago
No way, it's clearly a hot site.
MI
Micheline 1 year ago
Surprised it's not just backup!
LI
Lisbeth 1 year ago
I thought warm sites were for this?
CH
Chauncey 1 year ago
That's definitely a hot site setup!
ER
Erick 1 year ago
I'm a bit confused; I thought offsite storage was more about data backup rather than failover. Is that correct?
TA
Tamar 1 year ago
This sounds similar to a practice question I did where a hot site was described as fully operational. I think B is the right answer.
AN
Angella 1 year ago
I remember studying about disaster recovery sites, and I feel like a warm site has some downtime, so it can't be that.
CH
Charlena 1 year ago
I think this might be a hot site since it mentions near instant failover, but I'm not entirely sure.
JE
Jerry 1 year ago
Ah, I see. Using a standalone variable to set the area of interest is a clever idea. That could definitely help improve the performance without changing the model itself.
MO
Monroe 1 year ago
I'm a bit confused by the wording of this question. It's not totally clear to me what specific "communication methods" they're looking for. I might need to spend a bit more time unpacking the question before answering.
LA
Lauryn 1 year ago
This seems like a straightforward question about the importance of confidentiality. I'm pretty confident I can identify the best answer.
AR
Aron 1 year ago
The OFAC screening looks like the most specific element. I'm leaning towards option D as something that might be negotiable.
0/2000 characters

Save Cancel