The following is a list of statements about stakeholders and stakeholder management.
a. A customer can be considered as a stakeholder in a project.
b. A supplier can be considered as a stakeholder in a project.
c. Stakeholders' positions do not remain static during the life of the project.
d. Communication must not be tailored to each stakeholder in the project.
Which of the following is correct?