Who must do all the work to make sure Product Backlog items conform to the Definition of "Done"? (Choose the best answer)
The Scrum Guide clearly assigns the responsibility for delivering a 'Done' Increment to the Developers: 'The Developers are the people in the Scrum Team that are committed to creating any aspect of a usable Increment each Sprint.' This includes all work---development, testing, integration, etc.---needed to meet the Definition of 'Done,' a shared commitment that ensures quality. Option A (Scrum Team) is too broad; while the Scrum Team collaborates, only the Developers perform the hands-on work. Option C (Product Owner) is incorrect---they manage the Product Backlog, not the execution. Option D (QA Specialists) introduces a role not defined in Scrum; quality is the Developers' collective responsibility. Option E (Scrum Master) is wrong---they facilitate, not build. Thus, B is correct.