True or False: Scrum mandates the use of burndown charts.
Scrum does not mandate specific tools like burndown charts; it focuses on outcomes (e.g., a 'Done' Increment) rather than prescriptive practices. The Scrum Guide mentions progress tracking as optional: 'Various practices exist to forecast progress, like burn-downs, burn-ups, or cumulative flows. While proven useful, these do not replace the importance of empiricism.'
A: False---burndown charts are optional.
B: Correct---no mandate exists.
Exact Extract from Scrum Guide: 'Various practices exist to forecast progress, like burn-downs, burn-ups, or cumulative flows. While proven useful, these do not replace the importance of empiricism. In complex environments, what will happen is unknown.' (Section: 'Scrum Artifacts')
Thus, B is correct.
Annalee
9 months agoDetra
9 months agoEliz
9 months agoKarl
9 months agoDelsie
9 months agoBerry
10 months agoBarney
10 months agoAntione
10 months agoWei
10 months agoCora
10 months agoVanda
11 months agoBuddy
11 months agoTracie
11 months agoMarva
1 year agoGwenn
1 year agoErnestine
1 year agoRoxane
1 year agoAlline
1 year agoDominic
1 year agoLawrence
1 year agoAlfreda
1 year agoHaydee
1 year agoLura
1 year agoBettye
1 year agoFelix
1 year agoAdrianna
1 year agoBettye
1 year ago