True or False: Scrum mandates the use of burndown charts.
Scrum does not mandate specific tools like burndown charts; it focuses on outcomes (e.g., a 'Done' Increment) rather than prescriptive practices. The Scrum Guide mentions progress tracking as optional: 'Various practices exist to forecast progress, like burn-downs, burn-ups, or cumulative flows. While proven useful, these do not replace the importance of empiricism.'
A: False---burndown charts are optional.
B: Correct---no mandate exists.
Exact Extract from Scrum Guide: 'Various practices exist to forecast progress, like burn-downs, burn-ups, or cumulative flows. While proven useful, these do not replace the importance of empiricism. In complex environments, what will happen is unknown.' (Section: 'Scrum Artifacts')
Thus, B is correct.
Annalee
4 months agoDetra
4 months agoEliz
4 months agoKarl
4 months agoDelsie
5 months agoBerry
5 months agoBarney
5 months agoAntione
5 months agoWei
5 months agoCora
6 months agoVanda
6 months agoBuddy
6 months agoTracie
6 months agoMarva
11 months agoGwenn
11 months agoErnestine
11 months agoRoxane
10 months agoAlline
10 months agoDominic
10 months agoLawrence
11 months agoAlfreda
10 months agoHaydee
11 months agoLura
11 months agoBettye
11 months agoFelix
11 months agoAdrianna
12 months agoBettye
1 year ago