True or False: Scrum mandates the use of burndown charts.
Scrum does not mandate specific tools like burndown charts; it focuses on outcomes (e.g., a 'Done' Increment) rather than prescriptive practices. The Scrum Guide mentions progress tracking as optional: 'Various practices exist to forecast progress, like burn-downs, burn-ups, or cumulative flows. While proven useful, these do not replace the importance of empiricism.'
A: False---burndown charts are optional.
B: Correct---no mandate exists.
Exact Extract from Scrum Guide: 'Various practices exist to forecast progress, like burn-downs, burn-ups, or cumulative flows. While proven useful, these do not replace the importance of empiricism. In complex environments, what will happen is unknown.' (Section: 'Scrum Artifacts')
Thus, B is correct.
Marva
2 months agoGwenn
2 months agoErnestine
2 months agoRoxane
1 months agoAlline
1 months agoDominic
2 months agoLawrence
3 months agoAlfreda
2 months agoHaydee
2 months agoLura
2 months agoBettye
3 months agoFelix
3 months agoAdrianna
3 months agoBettye
3 months ago