When is the Sprint Backlog created? (Choose the best answer)
The Sprint Backlog is created during Sprint Planning as the Developers select items and plan delivery. The Scrum Guide states: 'Sprint Planning initiates the Sprint by laying out the work to be performed for the Sprint. This resulting plan is created by the collaborative work of the entire Scrum Team.'
A: Pre-planning creation isn't supported; it's a Sprint-specific plan.
B: It starts in planning, though it evolves during the Sprint.
C: Refinement prepares the Product Backlog, not the Sprint Backlog.
D: Correct---initial creation occurs here.
Exact Extract from Scrum Guide: 'The Sprint Backlog is composed of the Sprint Goal (why), the set of Product Backlog items selected for the Sprint (what), as well as an actionable plan for delivering the Increment (how)... Sprint Planning results in the Sprint Backlog.' (Section: 'Sprint Planning')
Thus, D is correct.
Audrie
2 months agoMoon
2 months agoLeslee
3 months agoVirgie
3 months agoTheron
3 months agoLavelle
3 months agoPearline
4 months agoJosephine
4 months agoJacquelyne
4 months agoShenika
4 months agoViva
4 months agoSantos
5 months agoGabriele
5 months agoHeike
9 months agoRosalia
9 months agoShawn
9 months agoAudra
9 months agoElena
8 months agoDelmy
8 months agoLeonora
8 months agoVelda
9 months agoKati
9 months agoClaribel
9 months agoMaryanne
9 months agoNarcisa
10 months agoLeanora
11 months agoRoosevelt
11 months ago