GAQM APM-001 Exam - Topic 6 Question 78 Discussion

The stakeholder register is an output of:
A) Identify Stakeholders.
B) Plan Stakeholder Management.
C) Control Stakeholder Engagement.
D) Manage Stakeholder Engagement.

GAQM APM-001 Exam - Topic 6 Question 78 Discussion

Actual exam question for GAQM's APM-001 exam
Question #: 78
Topic #: 6
[All APM-001 Questions]

The stakeholder register is an output of:

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Ashlyn
8 months ago
Wait, is it really just from Identify Stakeholders?
upvoted 0 times
...
Nieves
9 months ago
I thought it was part of Plan Stakeholder Management?
upvoted 0 times
...
Martina
9 months ago
Totally agree, A is the right choice!
upvoted 0 times
...
Leota
9 months ago
Seems too simple, are we sure about that?
upvoted 0 times
...
Jillian
9 months ago
It's definitely an output of Identify Stakeholders.
upvoted 0 times
...
Glynda
10 months ago
I’m pretty certain that the stakeholder register is created during the Identify Stakeholders phase. It’s the first step in understanding who we need to engage with.
upvoted 0 times
...
Catrice
10 months ago
I’m a bit confused because I feel like the stakeholder management plan is also important, but I don’t recall it being the output of that process.
upvoted 0 times
...
Starr
10 months ago
I remember practicing a question like this, and I think it was about the initial identification of stakeholders. So, I would lean towards option A.
upvoted 0 times
...
Catalina
10 months ago
I think the stakeholder register comes from the Identify Stakeholders process, but I'm not completely sure.
upvoted 0 times
...
Janae
10 months ago
Wait, I thought the stakeholder register was used to control stakeholder engagement. I'm not totally confident, but I'll go with option C just in case.
upvoted 0 times
...
Chantay
11 months ago
Okay, I've got this. The stakeholder register is created during the Plan Stakeholder Management process, so the answer is B.
upvoted 0 times
...
Gladys
11 months ago
Hmm, I'm a bit unsure on this one. I know the stakeholder register is related to stakeholder management, but I can't quite remember which specific process it's an output of. I'll have to think this through carefully.
upvoted 0 times
...
Filiberto
11 months ago
This one seems straightforward - the stakeholder register is an output of the Identify Stakeholders process, so I'll go with option A.
upvoted 0 times
...
Malika
1 year ago
The stakeholder register is definitely an output of Plan Stakeholder Management. I mean, how else are you going to plan for those stakeholders if you don't have a register, am I right?
upvoted 0 times
Alberto
11 months ago
C) Control Stakeholder Engagement.
upvoted 0 times
...
Janey
1 year ago
B) Plan Stakeholder Management.
upvoted 0 times
...
Skye
1 year ago
A) Identify Stakeholders.
upvoted 0 times
...
...
Sage
1 year ago
Haha, this is a tricky one! I'm going to have to go with Plan Stakeholder Management. Gotta love those process groups, am I right?
upvoted 0 times
...
Han
1 year ago
I think it's not Control Stakeholder Engagement or Manage Stakeholder Engagement, as those processes focus on monitoring and managing stakeholder engagement, not creating the initial register.
upvoted 0 times
...
Elsa
1 year ago
Hmm, I'm not sure about this one. I'm going to go with Identify Stakeholders since that seems like the logical starting point for creating the stakeholder register.
upvoted 0 times
Justa
1 year ago
Yes, that's correct. The stakeholder register is indeed an output of Identify Stakeholders.
upvoted 0 times
...
Rocco
1 year ago
I think you're right, Identify Stakeholders is the correct answer.
upvoted 0 times
...
...
Minna
1 year ago
I believe it could also be an output of Plan Stakeholder Management, as we plan how to engage with stakeholders and update the register accordingly.
upvoted 0 times
...
Page
1 year ago
I agree with Cathern, because in Identify Stakeholders process, we identify all stakeholders and document their information in the stakeholder register.
upvoted 0 times
...
Tijuana
1 year ago
I think the stakeholder register is an output of Plan Stakeholder Management. That makes the most sense to me.
upvoted 0 times
Laquita
1 year ago
I agree with you, I think it's from Plan Stakeholder Management.
upvoted 0 times
...
Franchesca
1 year ago
I believe it comes from Manage Stakeholder Engagement.
upvoted 0 times
...
Emilio
1 year ago
I think it's actually an output of Identify Stakeholders.
upvoted 0 times
...
...
Cathern
1 year ago
I think the stakeholder register is an output of Identify Stakeholders.
upvoted 0 times
...