GAQM Exam APM-001 Topic 6 Question 78 Discussion

Actual exam question for GAQM's APM-001 exam
Question #: 78
Topic #: 6
[All APM-001 Questions]

The stakeholder register is an output of:

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Minna
2 days ago
I believe it could also be an output of Plan Stakeholder Management, as we plan how to engage with stakeholders and update the register accordingly.
upvoted 0 times
...
Page
6 days ago
I agree with Cathern, because in Identify Stakeholders process, we identify all stakeholders and document their information in the stakeholder register.
upvoted 0 times
...
Tijuana
11 days ago
I think the stakeholder register is an output of Plan Stakeholder Management. That makes the most sense to me.
upvoted 0 times
Emilio
4 days ago
I think it's actually an output of Identify Stakeholders.
upvoted 0 times
...
...
Cathern
18 days ago
I think the stakeholder register is an output of Identify Stakeholders.
upvoted 0 times
...