Which baselines make up the performance measurement baseline?
A) Scope baseline, cost baseline, and schedule baseline
B) Scope baseline, project management baseline, and quality baseline
C) Cost baseline, schedule baseline, and risk baseline
D) Cost baseline, project management baseline, and schedule baseline