What is the total float of the critical path?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Jennie
17 days ago
I bet the person who wrote this question is a real 'float' enthusiast. Get it? Float? Haha!
upvoted 0 times
Johnetta
1 days ago
A) Can be any number
upvoted 0 times
...
...
Reid
1 months ago
If the total float of the critical path is negative, does that mean the project is already behind schedule? Yikes!
upvoted 0 times
Sonia
11 hours ago
If the total float of the critical path is negative, does that mean the project is already behind schedule? Yikes!
upvoted 0 times
...
Marylyn
3 days ago
C) Zero or negative
upvoted 0 times
...
Lennie
27 days ago
B) Zero or positive
upvoted 0 times
...
Leonida
30 days ago
A) Can be any number
upvoted 0 times
...
...
Samira
1 months ago
I was tempted to choose option C, but then I remembered that the critical path has no slack, so the total float has to be zero.
upvoted 0 times
...
Beckie
2 months ago
I'm not a big fan of option A. The total float of the critical path definitely can't be 'any number'.
upvoted 0 times
Alease
17 days ago
Yeah, I think option B is the correct answer. Total float can't be negative.
upvoted 0 times
...
Samira
1 months ago
I agree, option A doesn't make sense. It has to be either zero or positive.
upvoted 0 times
...
...
Wilda
2 months ago
Hmm, I was thinking option D since the calendar can affect the total float, but zero or positive makes sense too.
upvoted 0 times
...
Rodolfo
2 months ago
I heard that the total float can be zero or negative if there are delays in the project.
upvoted 0 times
...
Cory
2 months ago
The total float of the critical path has to be zero or positive, so I'll go with option B.
upvoted 0 times
...
Kimberely
2 months ago
I believe it's either zero or positive, depending on the project schedule.
upvoted 0 times
...
Marvel
2 months ago
I think the total float of the critical path can be any number.
upvoted 0 times
...