GAQM APM-001 Exam - Topic 2 Question 17 Discussion

Actual exam question for GAQM's APM-001 exam
Question #: 17
Topic #: 2
[All APM-001 Questions]

When cost variance is negative and schedule variance is positive, the project is:

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

0/2000 characters
Mammie
4 months ago
Agreed, it's a tricky situation for sure!
upvoted 0 times
...
Viola
4 months ago
Wait, how can you be ahead of schedule but still over budget?
upvoted 0 times
...
Moon
4 months ago
Sounds like a classic case of being late but saving money!
upvoted 0 times
...
Weldon
4 months ago
I thought it was over budget and ahead of schedule?
upvoted 0 times
...
Jamal
4 months ago
Definitely under budget and behind schedule.
upvoted 0 times
...
Vicki
5 months ago
I feel like I saw something similar in our last review session, but I can't quite remember if that means we're ahead or behind overall.
upvoted 0 times
...
Margart
5 months ago
If the cost variance is negative and the schedule variance is positive, it sounds like we're behind schedule but maybe saving money?
upvoted 0 times
...
Juan
5 months ago
I remember a practice question where a negative cost variance indicated we were spending more than planned, but I can't recall what that means for the schedule.
upvoted 0 times
...
Whitley
5 months ago
I think when cost variance is negative, it means we're over budget, but I'm not sure how that fits with a positive schedule variance.
upvoted 0 times
...
Ciara
5 months ago
Hmm, I'm a bit unsure about this one. The question is asking about the capabilities, but the options seem to be describing specific features. I'll need to think this through carefully.
upvoted 0 times
...
Noel
5 months ago
I'm pretty sure the Manager process should include the PURGEOLDEXTRACTS parameter to trigger the trail file clean-up, since it has the overall control and coordination of the GoldenGate processes.
upvoted 0 times
...

Save Cancel