When cost variance is negative and schedule variance is positive, the project is:

Suggested Answer: B

Get Premium APM-001 Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
11 comments · newest first
MA
Mammie 12 months ago
Agreed, it's a tricky situation for sure!
VI
Viola 12 months ago
Wait, how can you be ahead of schedule but still over budget?
MO
Moon 12 months ago
Sounds like a classic case of being late but saving money!
WE
Weldon 1 year ago
I thought it was over budget and ahead of schedule?
JA
Jamal 1 year ago
Definitely under budget and behind schedule.
VI
Vicki 1 year ago
I feel like I saw something similar in our last review session, but I can't quite remember if that means we're ahead or behind overall.
MA
Margart 1 year ago
If the cost variance is negative and the schedule variance is positive, it sounds like we're behind schedule but maybe saving money?
JU
Juan 1 year ago
I remember a practice question where a negative cost variance indicated we were spending more than planned, but I can't recall what that means for the schedule.
WH
Whitley 1 year ago
I think when cost variance is negative, it means we're over budget, but I'm not sure how that fits with a positive schedule variance.
CI
Ciara 1 year ago
Hmm, I'm a bit unsure about this one. The question is asking about the capabilities, but the options seem to be describing specific features. I'll need to think this through carefully.
NO
Noel 1 year ago
I'm pretty sure the Manager process should include the PURGEOLDEXTRACTS parameter to trigger the trail file clean-up, since it has the overall control and coordination of the GoldenGate processes.
0/2000 characters

Save Cancel