GAQM APM-001 Exam - Topic 1 Question 87 Discussion

When can pre-assignment of project team members occur?
D) When the project is the result of specific people being promised as part of a competitive proposal
A) When the project uses capital expenditures
B) When the required staff can be acquired from outside sources
C) When the project would be ignored due to travel expenses

GAQM APM-001 Exam - Topic 1 Question 87 Discussion

Actual exam question for GAQM's APM-001 exam
Question #: 87
Topic #: 1
[All APM-001 Questions]

When can pre-assignment of project team members occur?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

0/2000 characters
Hyun
7 hours ago
I agree, D makes sense. Specific people can drive success.
upvoted 0 times
...
Ivory
5 days ago
I think D is the best choice. Promises matter in proposals.
upvoted 0 times
...
Shakira
11 days ago
Yup, D makes the most sense in competitive situations!
upvoted 0 times
...
Dudley
16 days ago
A and B are also valid scenarios for pre-assignment.
upvoted 0 times
...
Karina
2 months ago
Wait, can you really pre-assign just because of travel costs? Seems odd.
upvoted 0 times
...
Lavelle
2 months ago
Totally agree, D is the right answer!
upvoted 0 times
...
Stephaine
2 months ago
Pre-assignment can happen when specific people are promised in proposals!
upvoted 0 times
...
Delfina
3 months ago
B is spot on! Outside sources can definitely help with staffing.
upvoted 0 times
...
Solange
3 months ago
Wait, can you really pre-assign just because of travel costs? Seems odd.
upvoted 0 times
...
Gwen
3 months ago
A is a bit off, right? Capital expenditures don’t guarantee pre-assignment.
upvoted 0 times
...
Nan
3 months ago
Totally agree with D! Makes sense for competitive bids.
upvoted 0 times
...
Vivan
3 months ago
Pre-assignment can happen when specific people are promised in proposals!
upvoted 0 times
...
Gail
3 months ago
I remember a practice question about travel expenses affecting project decisions, but I don't think that relates to pre-assignment. So, I guess it's not C.
upvoted 0 times
...
Hubert
4 months ago
I feel like we discussed how outside sources might affect team assignments, but I can't recall if that means pre-assignment is possible. Is it B?
upvoted 0 times
...
Marcos
4 months ago
I'm not entirely sure, but I remember something about capital expenditures being linked to team assignments. Could it be A?
upvoted 0 times
...
Glendora
4 months ago
I think pre-assignment can happen when specific people are promised in proposals, so maybe D is the right choice?
upvoted 0 times
...

Save Cancel