As part of your analysis, you discover that an incident is a false positive.

You change the incident status to Closed: False Positive.

Which statement about your update is true?

Suggested Answer: A

Study Guide p.105-p.106: incident analysis includes audit history, and incident settings/status should be kept up to date.

Technical Deep Dive: The correct answer is A. When an analyst changes an incident status to Closed: False Positive, FortiAnalyzer records the action in the incident audit history. That preserves accountability and allows other analysts to see what changed and why. The corresponding event is not automatically reclassified as mitigated. The incident is not deleted just because it is closed. The incident number remains stable because it is the identifier used to track the case through its lifecycle.


Get Premium FCP_FAZ_AN-7.6 Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
0 comments · newest first

Currently there are no comments in this discussion, be the first to comment!

0/2000 characters

Save Cancel