What is the minimum requirement for power feeds to a Rated-4 data center (ANSI/TIA-942)?
Suggested Answer: B
Get Premium CDCS Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
A Rated-4 facility requires dual active utility feeds, each from an independent substation, but they may come from the same utility provider if substations are geographically separate and independent.
Option A is too strict; ANSI/TIA-942 does not mandate two different companies.
Options C and D do not provide true independence and would fail Rated-4 requirements.
Thus, the minimum is two substations, possibly same provider.
26 comments · newest first
CA
Cassie
2 months ago
D is risky. One feed isn't enough for a Rated-4 center.
AN
Antonette
2 months ago
B could work too, but I prefer A for safety.
SA
Salena
2 months ago
I agree, A makes sense. Can't rely on just one power source.
MO
Mozelle
3 months ago
I think it's A. Two feeds from different substations are crucial for redundancy.
JO
Joana
3 months ago
C is risky, not enough backup.
SH
Sherita
3 months ago
B could work too, but not ideal.
KE
Kenny
3 months ago
I agree, A makes sense for redundancy.
LE
Leonida
3 months ago
I think it's A. Two feeds from different substations is crucial.
QU
Quentin
3 months ago
C is too risky. We need A for a Rated-4 center.
GE
Georgiana
4 months ago
B could work too, but I prefer A for safety.
EL
Elizabeth
4 months ago
I agree, A makes sense. Can't risk power from one source.
RO
Robt
4 months ago
I think it's A. Two feeds from different substations are crucial for redundancy.
KI
Kimberlie
4 months ago
C is definitely not enough for a Rated-4 data center!
MA
Mari
4 months ago
Wait, really? One power company isn't enough?
FI
Filiberto
6 months ago
I thought B was acceptable too, but I guess not?
VA
Vanna
6 months ago
Totally agree with A, redundancy is key!
GR
Gracia
6 months ago
A) Two feeds from two different substations, one power company not acceptable.
HA
Han
6 months ago
I thought one feed split into two boards would work, but guess not!
RU
Ruthann
6 months ago
C is definitely not enough for a Rated-4 data center.
MI
Micah
7 months ago
Wait, is B really acceptable? That seems risky.
RO
Rory
7 months ago
Totally agree with A, redundancy is key!
JE
Jeff
7 months ago
A) Two feeds from two different substations, one power company not acceptable.
BE
Benedict
7 months ago
I’m leaning towards A as well, but I’m confused about whether having two feeds from one substation could ever be acceptable.
AN
Annamae
7 months ago
I practiced a similar question, and I feel like C is definitely not enough for a Rated-4 data center.
ME
Merilyn
8 months ago
I remember something about redundancy in power feeds, so maybe B is correct since it allows for one power company.
PH
Phuong
8 months ago
I think the answer is A, but I’m not entirely sure if it has to be from different substations.