Exin Exam ASF Topic 10 Question 55 Discussion

Actual exam question for Exin's EXIN Agile Scrum Foundation exam
Question #: 55
Topic #: 10
[All EXIN Agile Scrum Foundation Questions]

A team estimates a Story using the Planning Poker technique. The team decides to allocate five Story points to the Story, because the Developers estimated two points and the Testers estimated three points.

Which statement is true regarding this scenario?

Show Suggested Answer Hide Answer
Suggested Answer: B