Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

EC-Council 312-76 Exam - Topic 1 Question 57 Discussion

Posted by Detra on Aug 22, 2022 at 05:48 AM

Which of the following measurements of a disaster recovery plan are aimed at avoiding an event from occurring?

Suggested Answer: D

Get Premium 312-76 Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
15 comments · newest first
ME
Meghann 11 months ago
Preventive measures? Seems too simple to be the only answer.
CA
Carmen 11 months ago
Totally agree with D, it’s all about prevention!
MA
Marg 12 months ago
Wait, are corrective measures really for prevention?
DA
Danica 12 months ago
I thought B was also about avoiding events?
LE
Lelia 1 year ago
Definitely D, preventive measures are key!
NA
Natalie 1 year ago
Preventive measures sound right, but I wonder if supportive measures could play a role too? I need to double-check that.
DI
Diane 1 year ago
I'm a bit confused; I thought corrective measures were also about preventing future issues, but now I'm not so sure.
JO
Johnson 1 year ago
I remember practicing a question like this, and I think detective measures are more about identifying issues after they happen, not preventing them.
ME
Melodie 1 year ago
I think preventive measures are definitely the right choice here, but I'm not entirely sure about the other options.
KA
Kate 1 year ago
Okay, I've got this. Based on my understanding, Cisco Unified Intelligence Center provides real-time and historical reports for contact center operations. I'll select those two options.
GA
Gaston 1 year ago
I remember practicing a question about EPGs where enabling unicast routing was key, so maybe option B is right?
JA
Jade 1 year ago
Okay, I've got this. The administrator wants automatic initial placement but no automatic migration, so the answer must be Partially Automated.
LA
Lawana 1 year ago
I'm a bit unsure about this one. The options seem to be describing different security features, but I'm not sure which one is the main function of TAILS. I'll have to review my notes and try to eliminate the options that don't seem quite right.
NA
Nada 1 year ago
Okay, let me see... Close Procurements, that's the process of completing and settling each procurement. I believe the right answer here is Contract plan, since that's the key document used to formally close out the procurement contracts.
AL
Alishia 1 year ago
Hmm, I'm not entirely sure about this one. I'll need to think it through carefully.
0/2000 characters

Save Cancel