CompTIA PK0-004 Exam

Certification Provider: CompTIA
Exam Name: CompTIA Project+
Duration: 90 Minutes
Number of questions in our database: 796
Exam Version: Aug. 06, 2022
PK0-004 Exam Official Topics:
  • Topic 1: Create a risk management plan, perform risk analysis, and develop a risk response plan/ Perform project closure activities
  • Topic 2: Develop a work breakdown structure and activity lists/ Identify the fundamentals of project management
  • Topic 3: Create effective communication, change management and transition plans/ Create project staffing and quality management plans
  • Topic 4: Develop a project schedule, identify the critical path and costs/ Monitor and control project performance, constraints, risks and procurements
  • Topic 5: Initiate a project, including creating project plans/ stakeholder strategies, and scope statement

Free CompTIA PK0-004 Exam Actual Questions

The questions for PK0-004 were last updated On Aug. 06, 2022

Question #1

The upper management team does not agree with certain aspects of a project. Which of the following would be the BEST way for the project manager to handle this situation?

Reveal Solution Hide Solution
Correct Answer: C

Question #2

Which of the following would be captured in a risk register?

Reveal Solution Hide Solution
Correct Answer: D

Question #3

A project manager has established a series of virtual meetings with project team members in different parts of the world. Team members from one country almost never show up to the meeting. Which of the following MOST likely describes why this occurring?

Reveal Solution Hide Solution
Correct Answer: B

Question #4

There is friction between team members who were on the team before a merger took place and those who transitioned during the merger. This situation is having an adverse effect on team performance. Which of the following can the project manager do to help resolve this issue?

Reveal Solution Hide Solution
Correct Answer: B

Question #5

Which of the following indicators would help the project manager to determine the financial status of the project?

Reveal Solution Hide Solution
Correct Answer: C


Unlock all PK0-004 Exam Questions with Advanced Practice Test Features:
  • Select Question Types you want
  • Set your Desired Pass Percentage
  • Allocate Time (Hours : Minutes)
  • Create Multiple Practice tests with Limited Questions
  • Customer Support
Get Full Access Now
Disscuss CompTIA PK0-004 Topics, Questions or Ask Anything Related

Save Cancel