What is the proper order of steps for installing an IX5000?

Show Suggested Answer Hide Answer
Suggested Answer: C

Installation Quick Reference

Move material and unpack (2 people required)

Install the lower display frames (2 people required)

(Systems that include seismic brackets only) measure, drill for, and install the seismic brackets (see the ''Installing the Seismic Bracket'' chapter on page C-1) (2 people required). Note that this step adds extra time to the installation.

Install the upper display frames (2 people required)

Install the cable runner

Install the upper crossbars, rear kick plates, and toe caps

Install the codecs, PDUs, subwoofer, speakers, and optional endpoint switches into the endpoint structure Note: The switches in the endpoint structure are optional items. The switches in the table legs to connect the Touch 10 device(s) are required for the Touch 10 device(s).

Install the table legs and electronic equipment (Ethernet/power modules for table legs, microphone connector (MC), PoE switch) for the front row table, and begin cabling procedures for the table (2 people required for some steps)

Perform cable routing for all installed equipment (codecs, PDUs, subwoofer, and speakers for the endpoint structure, and power/ laptop connectivity and PDUs for the table legs) AND place the cables for the light panels and camera

Install the displays, light panels, and camera, including cabling

Install the front kick plates and toe caps

Installl the front row tabletops (2 people required)

Install and cable the microphone bars, mute buttons, retractors/presentation cables

(IX5200 systems only) install and cable the second row table (2 people required for some steps)

Install the PET, fascias, display trim and thermoformed outer panels (2 people required)

Install software, register endpoint to Unified CM, perform first-time setup, run test calls

Room cleanup


http://www.cisco.com/c/dam/en/us/td/docs/telepresence/ix5000/assembly_guide/ix5000_install_gui de.pdf

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel