What is the purpose of a Project Audit?
Answer Options:
A Project Audit (p.141) occurs post-completion to assess:
Financial health
Performance evaluation
Lessons learned
It is not a planning tool (Option B), nor is it for active budget management (A) or solely for senior leadership (C). [P.141]