Daniel is a Project Manager and has just run a risk simulation to find out the likelihood of his project taking 3, 4, or 5 weeks to complete. He discovered it is equally likely the project would take any of those durations. What type of distribution is this?
A uniform distribution gives equal probability to all outcomes. Each project duration (3, 4, 5 weeks) has the same likelihood, making it uniformly distributed.