CIPS L4M8 Exam - Topic 4 Question 67 Discussion

What are the four quadrants in the Mendelow stakeholder matrix?
A) Explanation: Stakeholder are individuals or organizations that can be affected directly or indirectly by any project or decision. For successful procurement activities to take place, stakeholders must be identified, engaged and managed. Not all stakeholders require the same level of engagement and management. To appropriately manage identified stakeholders, the Mendelow management matrix has categorized stakeholders in four quadrants, according to how low or high their power and interest in the project could be. The four categories are: 1) Minimum effort (low power-Low interest) 2) Keep satisfied (high power-Low interest) 3) Keep informed (Low power -- high interest) 4) Manage closely (High power- High interest)

CIPS L4M8 Exam - Topic 4 Question 67 Discussion

Actual exam question for CIPS's L4M8 exam
Question #: 67
Topic #: 4
[All L4M8 Questions]

What are the four quadrants in the Mendelow stakeholder matrix?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Altha
2 months ago
Agreed! Engaging high power-high interest stakeholders is key.
upvoted 0 times
...
Lea
2 months ago
I feel like "manage closely" is the most important quadrant.
upvoted 0 times
...
Pa
3 months ago
Definitely! I remember them as low power-low interest, high power-low interest, and so on.
upvoted 0 times
...
Gerry
3 months ago
I think the four quadrants are crucial for project success.
upvoted 0 times
...
Ciara
3 months ago
Keep informed is crucial for low power stakeholders!
upvoted 0 times
...
Arlie
3 months ago
I thought there were more categories, but this makes sense.
upvoted 0 times
...
Gertude
3 months ago
Wait, are there really only four? Seems too simple.
upvoted 0 times
...
Malissa
3 months ago
Totally agree, it's all about managing priorities.
upvoted 0 times
...
Cherilyn
4 months ago
The four quadrants are spot on!
upvoted 0 times
...
Cortney
4 months ago
Wait, is this the one where we have to identify the four horsemen of the stakeholder apocalypse? Just kidding, I got this.
upvoted 0 times
...
Chan
4 months ago
Ah, the Mendelow matrix. Sounds like a delicious Italian dish, but I'm sure I can handle this question.
upvoted 0 times
...
Anisha
5 months ago
Hmm, let me think... Minimum effort, Keep satisfied, Keep informed, and Manage closely. Got it!
upvoted 0 times
...
Nenita
5 months ago
Mendelow's matrix is a classic tool for stakeholder management. I'm confident I can identify the four quadrants.
upvoted 0 times
...
Marguerita
5 months ago
The four quadrants are clearly defined. This should be an easy one.
upvoted 0 times
...
Junita
5 months ago
I recall that "Manage closely" is crucial for stakeholders with high power and interest. It’s like they’re the key players in the project!
upvoted 0 times
...
Helene
5 months ago
I’m a bit confused about the "Keep satisfied" quadrant. Does that mean we don’t need to engage them much?
upvoted 0 times
...
Glenn
6 months ago
I think the quadrants are about balancing power and interest, right? Like, I practiced a question where we had to categorize different stakeholders.
upvoted 0 times
...
Margo
6 months ago
I remember studying the Mendelow matrix, but I’m not entirely sure how to apply it in real scenarios.
upvoted 0 times
...
Alisha
6 months ago
Ah yes, the Mendelow stakeholder matrix. I remember those four quadrants now - minimum effort, keep satisfied, keep informed, and manage closely. Categorizing stakeholders based on their power and interest levels is such an important part of effective stakeholder management. I'll make sure I have that down pat for the exam.
upvoted 0 times
...
Elbert
6 months ago
The Mendelow matrix, that's the stakeholder analysis tool we learned about, right? Let's see, the four quadrants are... low power/low interest, high power/low interest, low power/high interest, and high power/high interest. I feel pretty good about remembering those, but I'll make sure to review the details before the test.
upvoted 0 times
...
Margart
6 months ago
Okay, the Mendelow matrix - that's the one that helps you categorize stakeholders based on their power and interest levels, right? I think the four quadrants are minimum effort, keep satisfied, keep informed, and manage closely. I'll double-check that before the exam just to be sure.
upvoted 0 times
...
Brett
6 months ago
Hmm, the Mendelow matrix... I know it has something to do with stakeholder management, but I'm a bit fuzzy on the specifics of the four quadrants. I'll have to review my notes to make sure I have them right.
upvoted 0 times
...
Nakita
7 months ago
I'm pretty confident I can remember the four quadrants of the Mendelow matrix. Let me think through them - low power/low interest, high power/low interest, low power/high interest, and high power/high interest.
upvoted 0 times
Elinore
12 days ago
The high power/high interest one is crucial to manage closely.
upvoted 0 times
...
Natalya
17 days ago
Same here! But I think I got it now.
upvoted 0 times
...
Arleen
2 months ago
I always mix up the quadrants.
upvoted 0 times
...
...

Save Cancel