Kirsty is designing a specification for a new contract and wants to include some qualitive KPIs for the new supplier, as well as quantitative. Which of the following could she include? Select TWO.
The correct answers are information sharing and trust. Further qualitative KPIs are listed on p.102. Deliveries in full and on time would be a quantitative KPI and early supplier involvement is not a KPI at all.