Which of the following are true statements about RFQ process? Select TWO that apply.
Request for quotations is often used when the only variable is price and the purchase value is under a financial threshold. This process is less formal than ITT. RFQ should be used in the following circumstances:
- Low-value, low-risk purchases
- When the specifications are sufficiently defined or the product/service is standardised
- Where the suppliers are pre-qualified
- Where there is a framework agreement which specifies the contract terms and conditions.
LO 1, AC 1.1