As a result of a global pandemic, a local hospital is facing significant patient capacity pressures and would like the construction of a new 50-bed ward to be prioritised and fully operational at the earliest opportunity. Which of the following pricing arrangements would support this aspiration?
Suggested Answer: A
Get Premium L4M3 Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
Incentivised pricing is designed to motivate suppliers to meet or exceed performance targets by providing financial or other incentives. In urgent projects, such as constructing a hospital ward during a pandemic, incentivised pricing encourages suppliers to accelerate delivery without compromising on quality. This supports the buyer's need for speed and reliability.
12 comments · newest first
CA
Cammy
2 months ago
Time and materials arrangement could lead to delays. Not ideal for urgent needs.
TH
Thad
3 months ago
I disagree. Fixed price economic adjustment pricing ensures budget control.
VE
Verdell
3 months ago
I think incentivised contract pricing is the best option. It motivates quick completion.
MA
Mari
3 months ago
Penetration pricing is usually for products, not construction projects.
JA
Jamal
3 months ago
Not sure if time and materials would actually get it done fast enough.
SH
Sherly
3 months ago
Really? I thought incentivised contracts were better for speed.
NO
Nobuko
4 months ago
Totally agree, fixed price seems the safest bet here!
RO
Robt
4 months ago
A fixed price economic adjustment could help manage costs effectively.
EL
Elza
4 months ago
Penetration contract pricing sounds familiar, but I can't recall how it would apply to a hospital project like this.
DO
Dorcas
4 months ago
I practiced a similar question, and I feel like time and materials arrangement pricing might lead to delays since it doesn't prioritize speed.
ED
Eden
4 months ago
I'm not entirely sure, but I remember something about fixed price economic adjustment pricing being useful for managing costs in uncertain situations.
VI
Viola
4 months ago
I think incentivised contract pricing could be beneficial since it encourages the contractor to finish the project quickly.