Gaskins Caskets (GC) is a manufacturing company that wants to identify new suppliers for a number of current parts. GC no longer has technical drawings for the parts and none of the engineers currently working for them have enough knowledge of the parts to write a specification. What could GC do to get accurate pricing from suppliers for these parts to compare to the existing parts?
B) GC could send samples of the parts to prospective suppliers as part of the request for quotation
A) GC's engineers could estimate the specification and drawings that are sent to prospective suppliers
C) GC could communicate a cost to the suppliers that must be met regardless of the final specification
D) GC could allow suppliers to develop and use their own specification as part of their cost proposal