Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

CIMA Exam CIMAPRO19-P02-1 Topic 8 Question 74 Discussion

Actual exam question for CIMA's CIMAPRO19-P02-1 exam
Question #: 74
Topic #: 8
[All CIMAPRO19-P02-1 Questions]

A manager must decide which one of three projects should be implemented. For each project the possible outcomes and their associated probabilities can be estimated reliably. The manager has decided to make the decision based solely on which project has the highest expected value of profit.

Which of the following statements are correct?

Select ALL that apply.

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Cyril
3 hours ago
Wait, why would the manager choose the project with the lowest standard deviation? That's not what the question is asking for. Option A is clearly wrong.
upvoted 0 times
...
Darrel
4 hours ago
But what about the standard deviation? Shouldn't the manager also consider that to assess the risk involved?
upvoted 0 times
...
Sylvia
2 days ago
I agree with you, Johnna. It makes sense to go for the project that will bring in the most profit.
upvoted 0 times
...
Johnna
4 days ago
I think the manager will select the project with the highest expected value of profit.
upvoted 0 times
...
King
10 days ago
Hmm, the manager should focus on maximizing expected value, not minimizing risk. Option E seems the most appropriate.
upvoted 0 times
...

Save Cancel