Risk management can be represented as a four step process. The four steps, shown randomly, are:
1. Establish appropriate risk management policies.
2. Risks are identified by key stakeholders.
3. Risks are monitored on an ongoing basis.
4. Risks are evaluated according to the likelihood of occurrence and impact on the organization.
Which of the following is the correct order for the four steps?
Suggested Answer: D
Get Premium CIMAPRO19-P02-1 Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
9 comments · newest first
GE
Georgeanna
12 months ago
I agree with C, that’s how I learned it!
GE
Georgiana
1 year ago
2 should come first for sure, then 1!
ME
Meghann
1 year ago
Wait, are we sure about that? Seems off to me.
LA
Lazaro
1 year ago
I think it should be A, makes more sense.
AP
Apolonia
1 year ago
The correct order is definitely C!
JU
Juliann
1 year ago
Ah, I remember learning about this in class. I'm pretty confident I can figure this out.
CH
Charolette
1 year ago
If it's a serial interface with PPP, I believe it defaults to point-to-point. I practiced a similar question last week.
TO
Tom
1 year ago
Hmm, this looks tricky. A subpoena seems specific, but I don't think that would automatically change monitoring parameters.
BI
Billye
1 year ago
I'm a bit confused by this question. I know the communication model has things like sender, receiver, and channel, but I'm not sure which one specifically refers to the method of conveying the message. I'll have to review my notes to be sure.