An electricity company owns and operates a nuclear power station located ten miles from a large city. A recent and very extensive engineering examination of the power station concludes with the estimate that the probability of a major nuclear disaster within the next 20 years is 0.2%.
Which of the following best explains the relevance of quantifying the risk in that way?
Suggested Answer: A
Get Premium CIMAPRA19-P03-1 Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
24 comments · newest first
WI
Willetta
1 day ago
I feel like A is the most responsible choice.
DE
Denise
6 days ago
D shows the engineers' expertise, but is it enough?
JE
Jesusita
12 days ago
A highlights the seriousness of nuclear risks.
NO
Norah
17 days ago
C could protect the company legally.
IV
Ivette
22 days ago
But B seems too dismissive.
GA
Gaynell
27 days ago
I think A makes sense.
MA
Maryln
1 month ago
This question is tricky.
VI
Vilma
1 month ago
Right! It's about public safety, not just numbers.
LO
Lonny
1 month ago
Exactly, Lisa. The risk shouldn't be quantified as acceptable.
MO
Mohammad
2 months ago
But does that really matter if the risk is still there?
TE
Tesha
2 months ago
I lean towards option D. It shows the engineers know what they're doing.
VE
Verona
2 months ago
True, Mike, but that feels like shifting blame.
MA
Mattie
2 months ago
But isn't option C also valid? It could protect the company legally.
VI
Vilma
2 months ago
I agree, John. It's too serious to just brush off.
LO
Lonny
2 months ago
I think option A makes sense. No risk is acceptable for nuclear accidents.
WI
Wilda
3 months ago
Probability doesn't mean it's safe; we need better standards!
AN
Anissa
3 months ago
This just shows they can claim no negligence later.
TR
Tresa
3 months ago
Wait, how can we trust those numbers?
AR
Arthur
3 months ago
I think any risk is too much for a nuclear plant!
CY
Cyril
3 months ago
0.2% is really low, but still a risk.
RO
Ronnie
3 months ago
I vaguely recall that D might be misleading. Just because they calculated a probability doesn’t necessarily mean they’re experts. It feels like a tricky option.
YV
Yvonne
4 months ago
I practiced a similar question where the focus was on accountability. I think C makes sense because it could protect the directors legally if something goes wrong.
EI
Eileen
4 months ago
I’m not sure, but I feel like B could be a possibility since 0.2% seems really low. Maybe it’s something we shouldn’t worry about too much?
WI
William
4 months ago
I remember discussing how risk quantification can be tricky, especially with something as serious as nuclear power. I think A might be the right choice since any risk could be unacceptable.