Independence Day Deal! Unlock 25% OFF Today – Limited-Time Offer - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

CIMA Exam CIMAPRA19-P03-1 Topic 4 Question 65 Discussion

Actual exam question for CIMA's CIMAPRA19-P03-1 exam
Question #: 65
Topic #: 4
[All CIMAPRA19-P03-1 Questions]

Having carried out a full capital appraisal for a construction project, HCompanyhasapproved the project with initial outflows of $6,000,000 anda net present value of $1,200,000.

The implementation phase has been commenced with 25% of the costs already committed.However whenthe ground was opened, an underground waterway was revealedwhich will need to be diverted if the project is to proceed. Work to carry out this diversion has been estimated at $1,300,000.

Which of the following factors will define whether the project should go ahead or not?

Show Suggested Answer Hide Answer
Suggested Answer: A, B, C

Contribute your Thoughts:

Alaine
2 months ago
Ha! Unexpected costs? That's the story of every construction project, isn't it? The project managers must be pulling their hair out right now.
upvoted 0 times
Dean
19 days ago
Julieta: I wonder how they will decide whether to proceed or not with this new cost.
upvoted 0 times
...
Julieta
20 days ago
User 2: Definitely, it's a common challenge project managers face.
upvoted 0 times
...
Shizue
27 days ago
User 1: Yeah, unexpected costs always seem to pop up in construction projects.
upvoted 0 times
...
...
Nan
2 months ago
The question is asking about the factors that will define whether the project should go ahead or not. I think option B is the correct answer - the negative NPV is the key factor here.
upvoted 0 times
Elena
11 days ago
So we need to consider both the negative NPV and the impact on shareholder confidence before making a decision.
upvoted 0 times
...
Alecia
15 days ago
That's a good point. Option C mentions that abandoning the project will have an adverse effect on shareholder confidence.
upvoted 0 times
...
Gianna
1 months ago
But what about the impact on shareholder confidence if we abandon the project?
upvoted 0 times
...
Sheridan
2 months ago
I think option B is the correct answer - the negative NPV is the key factor here.
upvoted 0 times
...
...
Ezekiel
2 months ago
This is a tricky one. The project was initially approved, but now there's a major unexpected cost. Shareholder confidence is definitely a factor to consider.
upvoted 0 times
Carline
27 days ago
C) Abandoning the project will have an adverse effect on shareholder confidence.
upvoted 0 times
...
Kristin
1 months ago
B) The project now has a negative NPV.
upvoted 0 times
...
Nada
1 months ago
A) The project actually has a higher NPV than before.
upvoted 0 times
...
Delmy
1 months ago
C) Abandoning the project will have an adverse effect on shareholder confidence.
upvoted 0 times
...
Aja
1 months ago
E) There may be other unexpected costs to be met if the project continues.
upvoted 0 times
...
Glory
2 months ago
A) The project actually has a higher NPV than before.
upvoted 0 times
...
...
Shenika
2 months ago
Hmm, the project has already incurred significant costs, but the NPV is now negative. I wonder if the additional cost of diverting the waterway will outweigh the expected benefits.
upvoted 0 times
...
Antonio
2 months ago
True, that could impact the project's NPV. We need to consider all factors before making a decision.
upvoted 0 times
...
Felicitas
3 months ago
But what about the additional cost of diverting the underground waterway?
upvoted 0 times
...
Antonio
3 months ago
I think the project should still go ahead.
upvoted 0 times
...

Save Cancel