M built a large factory last year and it has just been completed. The initial outflows on this project have a present value of $400 million and the entire project has a net present value of $30 million.
The initial phase of the project caused problems and there was an overspend of $35 million as there was unstable soil. The foundations had to be underpinned with large steel bars to ensure the building would be safe. There was no other suitable site for the project.
Theconstruction could not be abandoned as the site would have hadvery little commercial value.
The Internal Audit department has been asked to carry out a post completion audit. What issues should it concentrate on?
Maurine
15 hours agoEssie
8 days agoMakeda
9 days agoNakisha
14 days agoJani
17 days ago