Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

CIMA Exam CIMAPRA19-P03-1 Topic 1 Question 44 Discussion

Actual exam question for CIMA's CIMAPRA19-P03-1 exam
Question #: 44
Topic #: 1
[All CIMAPRA19-P03-1 Questions]

M built a large factory last year and it has just been completed. The initial outflows on this project have a present value of $400 million and the entire project has a net present value of $30 million.

The initial phase of the project caused problems and there was an overspend of $35 million as there was unstable soil. The foundations had to be underpinned with large steel bars to ensure the building would be safe. There was no other suitable site for the project.

Theconstruction could not be abandoned as the site would have hadvery little commercial value.

The Internal Audit department has been asked to carry out a post completion audit. What issues should it concentrate on?

Show Suggested Answer Hide Answer
Suggested Answer: B, C, E

Contribute your Thoughts:

Maurine
15 hours ago
Focusing on documentation and proper procedures is the way to go. That'll help identify any gaps or mistakes that were made during the project.
upvoted 0 times
...
Essie
8 days ago
The audit should definitely look at the initial survey report to see if the unstable soil was mentioned. If the survey missed it, that's a big issue that needs to be addressed.
upvoted 0 times
...
Makeda
9 days ago
But shouldn't the audit also look into who was responsible for the overspend?
upvoted 0 times
...
Nakisha
14 days ago
I agree, we need to learn from this experience to avoid similar issues in the future.
upvoted 0 times
...
Jani
17 days ago
I think the audit should focus on lessons for future projects.
upvoted 0 times
...

Save Cancel