New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Certinia PSA-Sysadmin Exam - Topic 2 Question 46 Discussion

Actual exam question for Certinia's PSA-Sysadmin exam
Question #: 46
Topic #: 2
[All PSA-Sysadmin Questions]

You have set up a Flow to automatically assign a resource's manager to the approver field on Timecards. Users have reported that submitted Timecards are going to the Project Manager for approval and not the resource's manager. Of the following, which could be a reason for this?

Show Suggested Answer Hide Answer
Suggested Answer: C

Step-by-Step Comprehensive Detailed Explanation

Understanding the Timecard Approval Process in PSA

By default, the timecard approval process in Certinia PSA (formerly FinancialForce PSA) follows a specific hierarchy.

If the project is a billable project and the Project Manager field is filled, the Project Manager is automatically assigned as the approver for timecards.

If the Project Manager field is blank or the project is non-billable, PSA uses the resource's manager as the approver (based on the Manager field in the Salesforce User record).

How Flows Work in Assigning Approvers

If you have created a Flow to automatically assign the resource's manager as the timecard approver, it means you are trying to override the default approval process.

However, if the Assign Project Manager To Timecard Approver configuration option is enabled, PSA will still prioritize the Project Manager over the resource's manager, regardless of your Flow settings.

This would explain why submitted timecards are still being assigned to the Project Manager instead of the resource's manager.

Why the Other Options Are Incorrect

A . PSA requires that only Project Managers can approve Timecards

This is incorrect because PSA allows timecards to be approved by either the Project Manager or the Resource's Manager, depending on the project settings.

B . The process builder to assign the resource's manager is not active

While this could be a factor, the main reason is the configuration setting that forces the Project Manager to be the default approver.

Even if the Flow was working correctly, the Assign Project Manager To Timecard Approver setting would still take precedence.

How to Fix the Issue

Navigate to PSA Configuration Settings and check the Assign Project Manager To Timecard Approver setting.

If it is set to True, change it to False to allow the Flow to correctly assign the resource's manager as the approver.

Test by submitting a new timecard and verifying the assigned approver.

Reference and Verified Certinia PSA Documentation

PSA System Administration Guide: Timecard Approval Process.

FinancialForce PSA Approval Workflow: Default Approver Rules.


Contribute your Thoughts:

0/2000 characters
Susy
2 months ago
I thought we fixed that configuration already!
upvoted 0 times
...
Artie
2 months ago
Isn't it possible the process builder is just inactive?
upvoted 0 times
...
Roosevelt
2 months ago
I think option C is the issue here.
upvoted 0 times
...
Willow
3 months ago
Wait, are we sure PSA only allows Project Managers?
upvoted 0 times
...
Leonora
3 months ago
Totally agree, that setting can mess things up.
upvoted 0 times
...
Cristal
3 months ago
I think I saw a similar question in our practice exam, and it was about configuration settings affecting the approval process. Option C sounds familiar.
upvoted 0 times
...
Mireya
3 months ago
I feel like we discussed how PSA might have restrictions on approvals, so option A could be a possibility too.
upvoted 0 times
...
Wilburn
4 months ago
I’m not entirely sure, but I think if the process builder isn’t active, it wouldn’t assign the manager correctly. That could be option B?
upvoted 0 times
...
Nadine
4 months ago
I remember something about how the settings can override the Flow, so maybe option C is the issue?
upvoted 0 times
...
Viki
4 months ago
This seems straightforward to me. The process builder must not be active, so I'm going to go with option B.
upvoted 0 times
...
Rosendo
4 months ago
Ah, I think I've seen this issue before. If the "Assign Project Manager To Time card Approver" setting is enabled, that could definitely cause the problem described.
upvoted 0 times
...
Stacey
4 months ago
I'm a bit confused by this question. I'm not sure I fully understand the context or the different configuration options mentioned.
upvoted 0 times
...
Malcolm
5 months ago
Okay, let's see here. I'm pretty sure the process builder is the key here, so I'll focus on option B.
upvoted 0 times
...
Harley
5 months ago
Hmm, this seems like a tricky one. I'll need to carefully review the options and think through the possible reasons for the issue.
upvoted 0 times
...
Charolette
8 months ago
But what if option C is true? Maybe the configuration setting is causing the Timecards to go to the Project Manager instead.
upvoted 0 times
...
Peggie
8 months ago
I agree with Sylvie, if the process builder is not active, then the resource's manager won't be assigned as the approver.
upvoted 0 times
...
Sylvie
8 months ago
I think the reason could be option B, the process builder is not active.
upvoted 0 times
...
Annita
8 months ago
Wait, are you telling me that PSA actually requires Project Managers to approve Timecards? That's news to me! *scratches head*
upvoted 0 times
...
Adolph
8 months ago
Oh, I know this one! It's definitely the configuration option Assign Project Manager To Time card Approver being set to True. That's gotta be it.
upvoted 0 times
Lavelle
7 months ago
No, I don't think so. If the configuration option is set to True, that would override the process builder and send the Timecards to the Project Manager.
upvoted 0 times
...
Andree
8 months ago
But could it also be that the process builder to assign the resource's manager is not active?
upvoted 0 times
...
Yoko
8 months ago
That makes sense, the configuration option being set to True would definitely cause the Timecards to go to the Project Manager.
upvoted 0 times
...
...
Willard
8 months ago
Hmm, I think the issue is with the process builder not being active. That's the most likely culprit here.
upvoted 0 times
Paul
7 months ago
Let's focus on activating the process builder first and see if that resolves the problem.
upvoted 0 times
...
Karol
7 months ago
I think PSA requiring only Project Managers to approve Timecards is not the issue here.
upvoted 0 times
...
Rashida
7 months ago
Maybe we should check the configuration option as well, just to be sure.
upvoted 0 times
...
Lavina
8 months ago
I agree, the process builder not being active could definitely be causing the issue.
upvoted 0 times
...
...

Save Cancel