You are in the process of setting up your organization's Resources and learn that Resources in France will be working a 35-hour work week.
What will you need to do to set them up with the proper work calendar?
PSA allows for the creation of multiple work calendars to accommodate different regional working hours. The best approach to handle the 35-hour work week for French Resources is:
Create a separate Work Calendar specifically for France with a 35-hour work week.
Define the correct daily working hours (e.g., 7 hours per day for a standard 5-day workweek).
Include French holidays in the work calendar to ensure scheduling accuracy.
Assign the work calendar to all French resources so that utilization calculations and resource assignments reflect the correct working hours.
Option A (PSA only allows one work calendar) is incorrect because PSA supports multiple work calendars.
Option B (using a 40-hour calendar and adjusting utilization calculations manually) is incorrect because it leads to inconsistent resource utilization and planning errors.
Thus, the correct answer is C.