Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Certinia PSA-Sysadmin Exam - Topic 1 Question 64 Discussion

You are in the process of setting up your organization's Resources and learn that Resources in France will be working a 35-hour work week.What will you need to do to set them up with the proper work calendar?
C) Create a separate 35-hour work calendar and associate it to the French Resources, including any specific French Holidays.
A) As PSA only allows one work calendar, it is best to implement a 40-hour work calendar and then create a validation rule to only allow 35 hours a week.
B) As the Work Calendar mostly impacts Utilization, set them up with a 40-work calendar, and then include the 35-hour hour work week in your utilization calculations.

Certinia PSA-Sysadmin Exam - Topic 1 Question 64 Discussion

Actual exam question for Certinia's PSA-Sysadmin exam
Question #: 64
Topic #: 1
[All PSA-Sysadmin Questions]

You are in the process of setting up your organization's Resources and learn that Resources in France will be working a 35-hour work week.

What will you need to do to set them up with the proper work calendar?

Show Suggested Answer Hide Answer
Suggested Answer: C

PSA allows for the creation of multiple work calendars to accommodate different regional working hours. The best approach to handle the 35-hour work week for French Resources is:

Create a separate Work Calendar specifically for France with a 35-hour work week.

Define the correct daily working hours (e.g., 7 hours per day for a standard 5-day workweek).

Include French holidays in the work calendar to ensure scheduling accuracy.

Assign the work calendar to all French resources so that utilization calculations and resource assignments reflect the correct working hours.

Option A (PSA only allows one work calendar) is incorrect because PSA supports multiple work calendars.

Option B (using a 40-hour calendar and adjusting utilization calculations manually) is incorrect because it leads to inconsistent resource utilization and planning errors.

Thus, the correct answer is C.


PSA Sys Admin Essentials Student Guide Fall 20

Contribute your Thoughts:

0/2000 characters

Currently there are no comments in this discussion, be the first to comment!


Save Cancel