Currently Project Managers and Resource Managers are using Gantt. You do not want your Project Managers creating assignment, resource requests or milestones from the Gantt. Which of the following custom settings should you configure to hide these buttons?
To prevent Project Managers from creating Assignments, Resource Requests, or Milestones from the Gantt, the Gantt Global Settings must be configured:
Navigate to Custom Settings Gantt Global Settings.
Modify the settings to remove the ability for Project Managers to create Assignments, Resource Requests, and Milestones from the Gantt.
Save and apply the changes.
Option A (Project Task Gantt Global Settings) is incorrect because it does not control high-level permissions for assignments and requests.
Option C (Project Task Gantt Preferences) is incorrect because it only controls user-specific preferences.
Thus, the correct answer is B.
FF-PSA-v15-Customer-Overview_1.0
Marla
1 month agoAnnice
1 month agoFrank
2 months agoJamika
2 months agoDomonique
2 months agoArletta
2 months agoTegan
2 months agoMi
2 months agoMaryrose
3 months agoGianna
3 months agoKaycee
3 months agoJin
4 months agoZena
4 months agoVicki
4 months agoWilliam
4 months agoKasandra
4 months agoClemencia
4 months agoKiley
5 months agoPaz
5 months agoTommy
5 months agoBrande
5 months agoTom
5 months agoJesusa
5 months agoDyan
6 months agoShonda
6 months agoParis
20 days agoArthur
26 days agoHuey
1 month agoAlmeta
6 months agoBettina
6 months ago