Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Certinia Exam PSA-Sysadmin Topic 1 Question 36 Discussion

Actual exam question for Certinia's PSA-Sysadmin exam
Question #: 36
Topic #: 1
[All PSA-Sysadmin Questions]

A manager was looking at utilization for a resource for the last two months. The resource was identified as 80% utilized for each month, but the subtotal section showed 160% for the user for that same two month period.

How can the report be fixed to show 80% instead of 160%?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Hubert
25 days ago
Haha, I bet the manager is scratching their head over this one. Maybe they need to hire a wizard to fix the report!
upvoted 0 times
...
Cristal
1 months ago
Ooh, the 'Weighted' utilization setting could be the way to go. That might help consolidate the numbers correctly.
upvoted 0 times
Annett
22 days ago
User 2: That sounds like a good idea. It should help fix the report.
upvoted 0 times
...
Jacquline
28 days ago
User 1: I think we should go with option C and set the 'Utilization' setting to 'Weighted'.
upvoted 0 times
...
...
Lynda
1 months ago
Hmm, I'm not sure the work calendar adjustment would fix this. Seems like a problem with the way the subtotal is being calculated.
upvoted 0 times
...
Lorita
2 months ago
I'm not sure about that, maybe creating a Summary Level formula could also work to correct the subtotal calculation.
upvoted 0 times
...
Arlyne
2 months ago
This question is really tricky! I think the key is to understand how the utilization calculation is being done. The report seems to be double-counting the resource's time.
upvoted 0 times
Shonda
1 days ago
I agree, it seems like the report is counting the resource's time twice.
upvoted 0 times
...
Yoko
2 days ago
C) Set the 'Utilization' setting for Target Utilization Approach to 'Weighted'
upvoted 0 times
...
Mammie
5 days ago
B) Create a Summary Level formula so the subtotal is calculated and not summed
upvoted 0 times
...
Buddy
18 days ago
A) Adjust the Resource's work calendar to 40 hours and refresh the report
upvoted 0 times
...
...
Salley
2 months ago
I agree with Tanja, that seems like the most logical solution to fix the report.
upvoted 0 times
...
Tanja
2 months ago
I think we should adjust the resource's work calendar to 40 hours and refresh the report.
upvoted 0 times
...

Save Cancel