New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Certinia PSA-Sysadmin Exam - Topic 1 Question 36 Discussion

Actual exam question for Certinia's PSA-Sysadmin exam
Question #: 36
Topic #: 1
[All PSA-Sysadmin Questions]

A manager was looking at utilization for a resource for the last two months. The resource was identified as 80% utilized for each month, but the subtotal section showed 160% for the user for that same two month period.

How can the report be fixed to show 80% instead of 160%?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

0/2000 characters
Rodrigo
3 months ago
Adjusting the work calendar could help too, but not sure it’s the best fix.
upvoted 0 times
...
Lisandra
3 months ago
Totally agree with Sarah, that subtotal needs fixing.
upvoted 0 times
...
Angella
3 months ago
Wait, how can you get over 100% utilization?
upvoted 0 times
...
Magdalene
4 months ago
I think option B makes the most sense!
upvoted 0 times
...
Rebeca
4 months ago
Seems like a classic case of double counting.
upvoted 0 times
...
Lilli
4 months ago
I think I read that subtotals can be misleading if they just sum percentages. So, option B sounds like it could fix the issue, but I’m not 100% sure.
upvoted 0 times
...
Billye
4 months ago
I practiced a similar question where we had to adjust settings for utilization. I feel like option C could be relevant, but I’m not confident.
upvoted 0 times
...
Katie
4 months ago
I'm not entirely sure, but I think adjusting the work calendar could help. It seems like it might change how the utilization is calculated.
upvoted 0 times
...
Lenny
5 months ago
I remember something about how subtotals can sometimes just add up percentages instead of averaging them. Maybe option B is the right choice?
upvoted 0 times
...
Aleshia
5 months ago
I'm feeling pretty confident about this one. The key is to adjust the report settings to calculate the utilization correctly. Option C, setting the Utilization setting to 'Weighted', should do the trick.
upvoted 0 times
...
Dallas
5 months ago
Okay, I've got this. The issue is that the subtotal is summing the utilization instead of calculating the average. Option B to create a summary level formula is definitely the right fix here.
upvoted 0 times
...
Erick
5 months ago
Hmm, I'm a bit confused by this one. The utilization is showing as 80% for each month, but the subtotal is 160%. I'll need to think through this carefully to figure out the best approach.
upvoted 0 times
...
Veronica
5 months ago
This seems like a straightforward issue with the report calculation. I think option B, creating a summary level formula, is the way to go here.
upvoted 0 times
...
Hubert
10 months ago
Haha, I bet the manager is scratching their head over this one. Maybe they need to hire a wizard to fix the report!
upvoted 0 times
Chan
8 months ago
C) Set the 'Utilization' setting for Target Utilization Approach to 'Weighted'
upvoted 0 times
...
Onita
8 months ago
B) Create a Summary Level formula so the subtotal is calculated and not summed
upvoted 0 times
...
Aja
8 months ago
A) Adjust the Resource's work calendar to 40 hours and refresh the report
upvoted 0 times
...
...
Cristal
10 months ago
Ooh, the 'Weighted' utilization setting could be the way to go. That might help consolidate the numbers correctly.
upvoted 0 times
Tish
8 months ago
Annett: Agreed. Let's update the setting and refresh the report to check the results.
upvoted 0 times
...
Ilene
8 months ago
User 3: Let's give it a try and see if it resolves the issue.
upvoted 0 times
...
Annett
10 months ago
User 2: That sounds like a good idea. It should help fix the report.
upvoted 0 times
...
Jacquline
10 months ago
User 1: I think we should go with option C and set the 'Utilization' setting to 'Weighted'.
upvoted 0 times
...
...
Lynda
10 months ago
Hmm, I'm not sure the work calendar adjustment would fix this. Seems like a problem with the way the subtotal is being calculated.
upvoted 0 times
...
Lorita
11 months ago
I'm not sure about that, maybe creating a Summary Level formula could also work to correct the subtotal calculation.
upvoted 0 times
...
Arlyne
11 months ago
This question is really tricky! I think the key is to understand how the utilization calculation is being done. The report seems to be double-counting the resource's time.
upvoted 0 times
Shonda
9 months ago
I agree, it seems like the report is counting the resource's time twice.
upvoted 0 times
...
Yoko
9 months ago
C) Set the 'Utilization' setting for Target Utilization Approach to 'Weighted'
upvoted 0 times
...
Mammie
9 months ago
B) Create a Summary Level formula so the subtotal is calculated and not summed
upvoted 0 times
...
Buddy
9 months ago
A) Adjust the Resource's work calendar to 40 hours and refresh the report
upvoted 0 times
...
...
Salley
11 months ago
I agree with Tanja, that seems like the most logical solution to fix the report.
upvoted 0 times
...
Tanja
11 months ago
I think we should adjust the resource's work calendar to 40 hours and refresh the report.
upvoted 0 times
...

Save Cancel