An Insurance company has created 4 Blue Prism processes: 1. Change of Address
2 Claims Processing
3 Renewals
4 Order Letter
The Order Letter process is not a published process but is called as a sub process by each of the 3 other processes.
Each day at 6am a scheduler starts:
* 3 instances of the Renewals process on the same virtual machine
* 2 instances of the Claims Processing process on 2 different virtual machines
* 1 instance of the Change of Address process on its own virtual machine
How many licenses will be consumed by the running processes?