When should a program manager approve the closure of a component project?
A) When acceptance criteria of the project are met
B) When the project has delivered the protect benefits
C) When program deliverables are complete
D) When project deliverables are complete

BICSI RCDDv14.1 Exam - Topic 1 Question 77 Discussion

Actual exam question for BICSI's RCDDv14.1 exam
Question #: 77
Topic #: 1
[All RCDDv14.1 Questions]

When should a program manager approve the closure of a component project?

Show Suggested Answer Hide Answer
Suggested Answer: A