A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is hesitant to submit a change request, as it would extend the program schedule and require a scope change.
To whom should the change request be presented?
Suggested Answer: A
Get Premium RCDDv14.1 Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
12 comments · newest first
TA
Tawna
3 months ago
The PMO should handle it. They manage the overall process and can assess impacts.
NO
Noelia
4 months ago
I feel like the program customer should see it first. They might want the change.
JA
Janella
4 months ago
I think it should go to the program governance board. They make the big decisions.
TA
Taryn
4 months ago
I’m not sure, PMO might have a better handle on the implications.
SH
Shala
4 months ago
Totally agree with Cyril, governance board is the right call.
PE
Peggy
4 months ago
Wait, extending the schedule for more profit? Sounds risky!
ST
Stefany
6 months ago
I think the program customer should be consulted first. They might have insights.
CY
Cyril
6 months ago
Definitely should go to the program governance board. They make the big decisions!
ST
Steffanie
7 months ago
I thought the program governance board was the right choice, but what if the program customer has a strong opinion on the change? That could complicate things.
AN
Anjelica
7 months ago
I’m leaning towards the PMO because they handle project changes, but I could be mixing it up with another topic we covered.
KR
Kristel
7 months ago
I remember a similar question where we had to decide on stakeholders for change requests. I feel like the program customer might need to be involved too.
JA
Janae
7 months ago
I think the change request should go to the program governance board since they oversee major changes, but I'm not entirely sure.