Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

BICSI Exam RCDDv14 Topic 10 Question 31 Discussion

Actual exam question for BICSI's RCDDv14 exam
Question #: 31
Topic #: 10
[All RCDDv14 Questions]

Several issues are identified on one component project in a program During a meeting with that component's project manager, the program manager offers several suggested resolutions Two weeks later, they meet again to review progress The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule

What should the program manager do?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel