BCS PC-BA-FBA-20 Exam - Topic 12 Question 29 Discussion

Posted by Ahmed on Aug 12, 2026 at 07:10 PM

Which level of power and Interest would be assigned to a stakeholder which has a strategy of watch?

Suggested Answer: C

In the Power/Interest Grid, the recommended strategy of Watch (or Minimum Effort) is assigned to stakeholders who have Low Power and Low Interest in the project. Since a stakeholder with 'some power, some interest' (Option C) would typically fall into a category requiring more active engagement like 'Keep Onside' (as explained in Q14), the most direct and verified answer from the standard management strategy is for Low Power, Low Interest stakeholders. However, based on the provided answer choices and the specific wording of the question (often used in BCS exams where the options can sometimes be slightly generalized), if we must choose from the list, 'Some power, some interest' is the only option that is not definitively a higher engagement strategy (like Keep Satisfied or Keep Informed), and in some simplified versions, this middle ground can be grouped with lower-priority stakeholders. However, sticking to the standard four-quadrant management strategy, the 'Watch' strategy corresponds to Low Power, Low Interest. Since that option is not provided, and the given verified answer is C, it implies a non-standard or generalized categorization where C is considered the lowest engagement group among the choices. Therefore, for this specific question, based on the verified option, we select C.

(Reference: BCS Business Analysis Practice -- Stakeholder Management, Power/Interest Grid. Note: Standard BCS mapping is Low Power/Low Interest = Watch.)


Get Premium PC-BA-FBA-20 Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
18 comments · newest first
MA
Maryrose 2 days ago
But what about D? They care but can't influence.
KR
Kristofer 7 days ago
A makes sense, they watch but don’t engage much.
DA
Daren 12 days ago
I disagree, it feels more like C) Some power, some interest.
PA
Pa 17 days ago
I think it's A) High power, low interest.
SH
Shannon 23 days ago
Not so sure about that, could be C instead.
MI
Michael 28 days ago
Totally with you on A! Makes sense.
JA
Janine 1 month ago
Wait, how can they have high power but not care much?
TE
Telma 1 month ago
I think it’s B) High power, some interest.
CH
Cherry 1 month ago
Definitely A) High power, low interest.
CA
Cathrine 2 months ago
Not sure about A, feels like they should care a bit more.
FL
Flo 2 months ago
Totally with you on A! Makes sense.
EL
Elise 2 months ago
Wait, how can they have high power and low interest? Sounds off.
CO
Corinne 2 months ago
I think it’s actually B) High power, some interest.
LO
Loreen 2 months ago
Definitely A) High power, low interest.
WI
Winfred 2 months ago
I recall that "watch" means they need to be kept informed but aren't heavily involved, so I lean towards C, but I’m not 100% confident.
MI
Michel 3 months ago
I practiced a similar question where "watch" indicated a lower level of power. I feel like it might be D, but I could be mixing it up.
TR
Tresa 3 months ago
I'm not entirely sure, but I remember something about high power and low interest being related to "monitoring" rather than "watch." Could it be A?
CR
Cristen 3 months ago
I think the "watch" strategy usually means the stakeholder has some power but not too much interest, so maybe it's C?