Determining the schedule for each testing activity and test milestones for a test project, using activity estimates, available resources, and other constraints is a typical task performed during
Test planning involves defining the overall approach to testing, including scheduling, resources, and milestones. It is during this phase that the detailed schedule for each testing activity is determined based on estimates, resource availability, and constraints. The ISTQB CTFL Syllabus v4.0 outlines that test planning encompasses the creation of test plans and schedules to ensure that testing activities are properly managed and controlled.