[Installing AV Systems]Upon completion of hardware installation and configuration for a new deployment, the NEXT thing the AV Project Manager should have scheduled is
B) testing and verification.
A) training the client.
C) invoicing and project close out.
D) preventative maintenance schedule.

Avixa CTS Exam - Topic 3 Question 41 Discussion

Actual exam question for Avixa's CTS exam
Question #: 41
Topic #: 3
[All CTS Questions]

[Installing AV Systems]

Upon completion of hardware installation and configuration for a new deployment, the NEXT thing the AV Project Manager should have scheduled is

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

0/2000 characters
Jeniffer
5 days ago
I think A) training the client should come first. They need to know how to use it!
upvoted 0 times
...
Dorthy
10 days ago
Definitely B) testing and verification. Can't skip that step!
upvoted 0 times
...
Edda
15 days ago
I practiced a question similar to this, and I think it was about scheduling training first, but testing seems crucial too.
upvoted 0 times
...
Wilson
20 days ago
I feel like invoicing and project close out might come later, but I can't recall if we should do that before or after testing.
upvoted 0 times
...
Emogene
26 days ago
I'm not entirely sure, but I remember something about training the client being important right after installation.
upvoted 0 times
...
Stefanie
1 month ago
I think the next step should be testing and verification, right? We need to ensure everything works before moving on.
upvoted 0 times
...