In the scope of work (SOW), an interface is described as being installed in the lectern. While the work is underway onsite, the client asks for the interface to be moved to a table next to the lectern. What is the proper response from the technician?
If a client requests a change to the scope of work, such as relocating equipment, the technician should advise the project manager. This ensures that the request is documented and assessed for impact on the project scope, budget, and timeline, maintaining proper project management protocols.
CTS Technology Specialist Reference According to CTS standards, scope changes should be communicated to project management to ensure appropriate adjustments and approvals are made.
Antonio
9 months agoTresa
9 months agoElza
9 months agoRaymon
9 months agoLouvenia
9 months agoAlton
10 months agoSvetlana
10 months agoZona
10 months agoNaomi
10 months agoRaina
10 months agoMicah
11 months agoDanica
11 months agoMichael
11 months agoRenay
11 months agoAngelica
11 months agoValda
12 months agoSkye
12 months agoLettie
1 year agoMajor
1 year agoMammie
1 year agoElza
1 year agoTiera
1 year agoMarsha
1 year agoLizbeth
1 year agoVeta
1 year agoAnika
1 year agoXochitl
1 year agoCarisa
2 years agoSalome
2 years agoElinore
2 years ago