An issue is showing the Time Tracking section as follows:

There is clearly an hour's difference between the Original and Remaining estimates.

Identify two possible reasons Logged Time is showing as Not Specified. (Choose two.)

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Buck
5 days ago
I think option C could also be a reason. The hour's work was logged via a REST call by the user, which might have caused the discrepancy.
upvoted 0 times
...
Christoper
8 days ago
C and E could also be possible. If the work was logged via a REST call, it might not have the necessary details. And increasing the original estimate would create the hour's difference.
upvoted 0 times
...
Julianna
10 days ago
A and B seem like the most likely reasons. Time tracking needs to be enabled to log time, and adjusting the remaining estimate without logging effort would definitely result in Logged Time showing as Not Specified.
upvoted 0 times
...
Kendra
10 days ago
I agree with Chana. Another possible reason could be that the remaining estimate was adjusted without logging any effort.
upvoted 0 times
...
Chana
14 days ago
I think the reason Logged Time is showing as Not Specified could be because time tracking was not enabled when the work was logged.