Select the correct answer;
I . IEEE 829 contains a standard for test summary report. II.
Test reporting can occur at the end of the testing effort.
III . Percentage of test time lost due to blocking events is not a valid metric to monitor.
IV . Test summary report may contain summary of testing activities, versions of the software tested and management approvals.