An internal audit schedule should be prioritized on the basis of all of the following criteria EXCEPT the
C) size of the auditee's department
A) cost of the activities
B) risk of the activities
D) management's requests

ASQ CQA Exam - Topic 3 Question 130 Discussion

Actual exam question for ASQ's CQA exam
Question #: 130
Topic #: 3
[All CQA Questions]

An internal audit schedule should be prioritized on the basis of all of the following criteria EXCEPT the

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

0/2000 characters
Yen
1 day ago
Agreed, risk should always come first!
upvoted 0 times
...
Dahlia
6 days ago
Wait, management's requests? Really? That feels off.
upvoted 0 times
...
Lorita
11 days ago
C seems like a weird choice to prioritize.
upvoted 0 times
...
Elza
17 days ago
I think D is more important than people realize.
upvoted 0 times
...
Nicholle
22 days ago
Definitely not A, cost shouldn't be the main factor.
upvoted 0 times
...
Diane
27 days ago
I’m pretty confident that cost isn’t a primary criterion for prioritizing audits, but I might be mixing it up with another topic.
upvoted 0 times
...
Tyra
1 month ago
I feel like management's requests could be important, but I can't recall if they should take precedence over other factors.
upvoted 0 times
...
Raylene
1 month ago
I think we had a practice question that mentioned the size of the department shouldn't really affect the audit schedule.
upvoted 0 times
...
Sabra
1 month ago
I remember we discussed prioritizing audits based on risk and management requests, but I'm not sure about the cost factor.
upvoted 0 times
...