APMG-International Exam Better-Business-Cases-Practitioner Topic 4 Question 2 Discussion

Actual exam question for APMG-International's Better-Business-Cases-Practitioner exam
Question #: 2
Topic #: 4
[All Better-Business-Cases-Practitioner Questions]

Using the Scenario, answer the following questions about the Management Case section of the Full Business Case for

the Pittville project.

Decide whether the entry is appropriate for the document identified and select the responses that support your decision.

Remember to select 2 answers to each question.

The Programme and Project Management Framework section states:

1. The Programme Director is to be responsible for the Western Area Learning Improvements Programme.

2. Project progress reports are to be provided to the Consortium at the end of each month.

Which 2 statements apply to these entries?

Show Suggested Answer Hide Answer
Suggested Answer: A, E

Contribute your Thoughts:

Gabriele
1 years ago
I think we should remove entry 2 and document project reporting in the Project Plan.
upvoted 0 times
...
Jamika
1 years ago
I believe no change is needed for entry 1. It seems appropriate to me.
upvoted 0 times
...
Ahmed
1 years ago
I agree with Shasta. The Programme Director shouldn't be solely responsible.
upvoted 0 times
...
Shasta
1 years ago
I think we should amend entry 1 because the Consortium should be jointly accountable.
upvoted 0 times
...
Glory
1 years ago
No changes to entry 2 make sense. The project framework should include reporting arrangements in relation to the programme. It's all about that sweet, sweet communication, am I right?
upvoted 0 times
Veronika
1 years ago
Absolutely, communication is key in any project. It's important to have clear reporting structures in place.
upvoted 0 times
...
Graciela
1 years ago
No change to entry 2, because the project framework should include project reporting arrangements in relation to the programme.
upvoted 0 times
...
...
Otis
1 years ago
Haha, entry 2 should definitely be removed. Project reporting arrangements belong in the Project Plan, not the Programme Framework. Someone's been watching too many episodes of 'The Office'!
upvoted 0 times
...
Antonette
1 years ago
I agree with amending entry 1. The Senior Responsible Owner should not be the Programme Director, that's not appropriate. C'mon, that's just basic governance!
upvoted 0 times
Gertude
1 years ago
B) Amend entry 1, because the Senior Responsible Owner should NOT be the Programme Director.
upvoted 0 times
...
Breana
1 years ago
A) Amend entry 1, because the Western Area Learning Consortium should be jointly accountable for the Programme.
upvoted 0 times
...
...
Kelvin
1 years ago
I think entry 1 should be amended because the Western Area Learning Consortium should be jointly accountable for the Programme. The Programme Director shouldn't be solely responsible.
upvoted 0 times
Josue
1 years ago
I agree, the Consortium should share responsibility for the Programme.
upvoted 0 times
...
Cristen
1 years ago
B) Amend entry 1, because the Senior Responsible Owner should NOT be the Programme Director.
upvoted 0 times
...
Earleen
1 years ago
A) Amend entry 1, because the Western Area Learning Consortium should be jointly accountable for the Programme.
upvoted 0 times
...
...